Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
95
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Washery Part:
Progress of work:
1. Design & Engineering : 70.00 %
2. Civil Work : 42.00 %
3. Structural Fabrication : 4.00 %
4. Supply of P&M : 13.00 %
Progress of construction by BOM operator M/S ACB is very slow due to their financial crisis. Procurement and supply of P&M items started.
Renovation / Strengthening of Railway Infrastructure: LOA for Phase III has been issued to M/s RITES Limited on 14.03.2020. Tender for Civil Package was floated by M/s RITES in May’2020 but cancelled due to technical reason. Fresh tender was floated on 30.10.2020. Technical bid was opened on 24.11.2020 and Price Bid was opened on 24.03.2021. LOA was issued to lowest bidder M/s Allied Infrastructure & Projects Pvt Limited by M/S RITES on 29.04.2021. Supply of rail has been completed. S&T Work has been combined with 5.0 MTPA Patherdih Coal Washery. Civil work & OHE work is going on. | Washery Part:
Progress of work:
1. Design & Engineering : 57.0 %
2. Civil & Structural Works : 24.5 %
3. Supply of P&M : 13.0 %
Renovation / Strengthening of Railway Infrastructure: LOA for Phase III has been issued to M/s RITES Limited on 14.03.2020. Tender for Civil Package was floated by M/s RITES in May’2020 but cancelled due to technical reason. Fresh tender was floated on 30.10.2020. Technical bid was opened on 24.11.2020 and Price Bid was opened on 24.03.2021. LOA was issued to lowest bidder M/s Allied Infrastructure & Projects Pvt Limited by M/S RITES on 29.04.2021. Civil work is going on (about 65% complete). Supply of rail is going on (85% complete). OHE work is going on (8% complete). |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |