Project Summary
Project Summary
Sector Name : COAL.
Agency Name : BHARAT COKING COAL LIMITED.
Project Name : PATHERDIH 2.5 NLW COAL WASHERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    95

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
334.270334.27

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
132.742.51.61135.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20180/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1000

Ministry Review Date

LatestLastPhysical Progress (%)Status
45.05Ongoing

Monthly Status

Background Information

Washery Part: Progress of work: 1. Design & Engineering : 70.00 % 2. Civil Work : 42.00 % 3. Structural Fabrication : 4.00 % 4. Supply of P&M : 13.00 % Progress of construction by BOM operator M/S ACB is very slow due to their financial crisis. Procurement and supply of P&M items started. Renovation / Strengthening of Railway Infrastructure: LOA for Phase III has been issued to M/s RITES Limited on 14.03.2020. Tender for Civil Package was floated by M/s RITES in May’2020 but cancelled due to technical reason. Fresh tender was floated on 30.10.2020. Technical bid was opened on 24.11.2020 and Price Bid was opened on 24.03.2021. LOA was issued to lowest bidder M/s Allied Infrastructure & Projects Pvt Limited by M/S RITES on 29.04.2021. Supply of rail has been completed. S&T Work has been combined with 5.0 MTPA Patherdih Coal Washery. Civil work & OHE work is going on.Washery Part: Progress of work: 1. Design & Engineering : 57.0 % 2. Civil & Structural Works : 24.5 % 3. Supply of P&M : 13.0 % Renovation / Strengthening of Railway Infrastructure: LOA for Phase III has been issued to M/s RITES Limited on 14.03.2020. Tender for Civil Package was floated by M/s RITES in May’2020 but cancelled due to technical reason. Fresh tender was floated on 30.10.2020. Technical bid was opened on 24.11.2020 and Price Bid was opened on 24.03.2021. LOA was issued to lowest bidder M/s Allied Infrastructure & Projects Pvt Limited by M/S RITES on 29.04.2021. Civil work is going on (about 65% complete). Supply of rail is going on (85% complete). OHE work is going on (8% complete).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone