Washery (BOM Part):
Progress of work:
1. Design & Engineering : 100 %
2. Civil Construction : 99 %
3. Structural Fabrication : 96 %
4. Erection & Commissioning : 95 %
5. Supply of P&M : 97 %
Due to financial crisis of M/s ACB (India) Limited, the progress of work is not satisfactory. BCCL has disbursed adjustable advance in five equal installments totaling Rs. 50.40 Cr. to M/S ACBIL. Continuous Follow-up is being done with M/s ACB (India) Limited to complete the project at the earliest. RC 1, 2, 3, 4, 5, 6, 7, 8, 8A, 9, 10, 11 & 12 no load test is completed. 01 no. Four roll crusher no load test is completed. Construction of Switchyard, metering and charging completed on 30.12.2024. Equipment installed at washing section. Raw Coal receiving section (Up to Belt no. RC 13 including all equipment) completely ready. Load trial run done. Raw water for process of plant has reached at Washery. No Load Trial run of main Washery Building done on 22.01.2025.
Renovation / Strengthening of Railway Infrastructure: Revised LOA for Phase III has been issued to M/s RITES. Bridge and S&T work completed. Procurement & delivery of Rail also completed. Work of civil package is going on (about 98 % complete). About 98 % of OHE work completed. Total Length: 8.20 Tkm/1.50 Rkm.
Environmental Clearance: Consent to operate has been granted by WBPCB, Kolkata on 10.01.2025. | Washery Part:
Progress of work:
1. Design & Engineering : 100 %
2. Civil & Structural Works : 96 %
3. Supply of P&M : 84 %
4. Erection & commissioning : 54 %
Due to financial crisis of M/s ACB (India) Limited, the progress of work is not satisfactory. Continuous follow-up is being done with M/s ACB (India) Limited to complete the project at the earliest.
Renovation / Strengthening of Railway Infrastructure: Revised LOA for Phase III has been issued to M/s RITES. Work of civil package is going on (about 85% complete). Procurement & delivery of Rail complete. About 72% of OHE work and 84% of S&T work complete. |