Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : BAROUD OC EXPANSION (3-10 MTY).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 2 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2309.802309.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
901.410.114.84916.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/03/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
175.380

Ministry Review Date

LatestLastPhysical Progress (%)Status
25-APR-2547Ongoing

Monthly Status

Background Information

Notification of additional Land of 151.638 Ha, U/s 7(i) of CBA, (A&D) Act. Status- Achieved. Notification of additional 151.683 Ha land u/s 7(i) of CBA (A&D) Act granted by MoC on 18.06.2025Silo construction work completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks