Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : JAMPALI OCP RCE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
278.640278.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
208.41.24.69209.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20243/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3.120

Ministry Review Date

LatestLastPhysical Progress (%)Status
82Ongoing

Monthly Status

Background Information

Approval of Completion Report of Project Status- Completion Report is under process of approvalCompletion of the Project. Project has achieved 3 MT production in FY 2021-22 & 2022- 23 and approx. 70.51% capital expenditure incurred till date as per approved capital of Jampali RCE.Under preparation at Area.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone