Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : VENKATESH KHANI COAL MINE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 8 / 5 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
484.510484.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
318.1200318.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
110.260

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone