EC: MoEFCC issued Show Cause Notice on 30.04.2025. Reply submitted by Khadia Project on 21.05.2025. Further Site Visit by RO MoEFCC, Lucknow conducted on 30.06.2025. Amendment in TOR will be obtained after receipt of amendment in EC. FC:Demand Note for payment of amount of CA NPV to be issued by DFO Singrauli.4.0 Mtpa Incremental CHP:Overall Physical Progress :64 percentage. | 1.Environmental Clearance:Application for amendment in TOR (15.0 to 20.0 Mtpa) will be submitted after approval of Mining Plan (20.0 Mtpa).
2.Forest Land (57.906 Ha, Revised: 53.142 Ha):EDS raised by Govt. of MP on 13.10.2023. CF, Rewa forwarded the reply of query to NO(MP) on 15.11.2023. Govt. of MP forwarded the proposal to MoEFCC on 31.01.2024. EDS raised by MoEFCC to Govt. of MP on 28.02.2024. APCCF(LM)NO(MP) raised EDS to DFO, Singrauli on 07.03.2024. DFO, Singrauli has forwarded the EDS to Khadia Project on 14.03.2024.
3.CHP (4.0 Mtpa Incremental):4.0 Mtpa Incremental CHP: Site handed over on 17.03.2024(S.K Samantha).Soil test and topographical survey is under process.
|