Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : KHADIA EXPANSION OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 5 / 2 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
491.670491.67

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
138.724.8822.02185.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
66.430

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-SEP-2339.73Ongoing

Monthly Status

Background Information

1.Environmental Clearance:Closure report is awaited. Amendment in ToR will be obtained after receipt of amendment in EC. 2.Forest Land (57.906 Ha, Revised: 53.142 Ha): Meeting of FAC held on 26.05.2025 MoM awaited. 3.CHP (4.0 Mtpa Incremental):58 percent1.Environmental Clearance:Application for amendment in TOR (15.0 to 20.0 Mtpa) will be submitted after approval of Mining Plan (20.0 Mtpa). 2.Forest Land (57.906 Ha, Revised: 53.142 Ha):EDS raised by Govt. of MP on 13.10.2023. CF, Rewa forwarded the reply of query to NO(MP) on 15.11.2023. Govt. of MP forwarded the proposal to MoEFCC on 31.01.2024. EDS raised by MoEFCC to Govt. of MP on 28.02.2024. APCCF(LM)NO(MP) raised EDS to DFO, Singrauli on 07.03.2024. DFO, Singrauli has forwarded the EDS to Khadia Project on 14.03.2024. 3.CHP (4.0 Mtpa Incremental):4.0 Mtpa Incremental CHP: Site handed over on 17.03.2024(S.K Samantha).Soil test and topographical survey is under process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone