Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : DHUPTALA OC(SASTI UG TO OC).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   1.39

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7110720.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
159.1500159.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5.720

Ministry Review Date

LatestLastPhysical Progress (%)Status
33Ongoing

Monthly Status

Background Information

Notification U/s. 9(1) for 870.87 Ha land published on 29th January 2015, Gazette publication U/s. 11(1) published on 11th June 2015. Land compensation of Rs. 82.46 Cr against 417.93 Ha land (out of 821.62 Ha tenancy land) has been sanctioned on 30/12/2020. Compensation of Rs. 25.54 Cr against 127.02 ha land (out of 821.62 Ha tenancy land) sanctioned on 25/11/2021. Compensation of Rs.19.25 Cr against 97.01 Ha land sanctioned on 20/01/2022.Compensation of Rs 32.76 Cr against 167.17 Ha land sanctioned on 18-05-2022. For this tenancy land, Till date,physical possession obtained is 729.58 Ha, land compensation amount of Rs. 144.19.Crore.(Total possession is 771.38 Ha)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone