Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 1.39
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
6
/
6
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Notification U/s. 9(1) for 870.87 Ha land published on 29th January 2015, Gazette publication U/s. 11(1) published on 11th June 2015. Land compensation of Rs. 82.46 Cr against 417.93 Ha land (out of 821.62 Ha tenancy land) has been sanctioned on 30/12/2020. Compensation of Rs. 25.54 Cr against 127.02 ha land (out of 821.62 Ha tenancy land) sanctioned on 25/11/2021. Compensation of Rs.19.25 Cr against 97.01 Ha land sanctioned on 20/01/2022.Compensation of Rs 32.76 Cr against 167.17 Ha land sanctioned on 18-05-2022. For this tenancy land, Till date,physical possession obtained is 729.58 Ha, land compensation amount of Rs. 144.19.Crore.(Total possession is 771.38 Ha) |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |