Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : RCE OF KAKATHIYAKHANI OC - 2 PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
442.420442.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
202.61.390203

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
16.380

Ministry Review Date

LatestLastPhysical Progress (%)Status
63Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone