Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : RCE OF KISTARAM OPENCAST PROJECT.

Reported Date : 14-DEC-23

Monthly Report : 12 / 2023

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.040164.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
143.081.020144.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11.980

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks