Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : ADASA UG TO OC (1.50 MTY).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 4 / 2 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3160333.43

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
208.200208.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20243/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.550

Ministry Review Date

LatestLastPhysical Progress (%)Status
78Ongoing

Monthly Status

Background Information

Notification u/s 11(1) for 321.13Ha land has been issued on 07/10/2021, Gazette publication issued on 09/10/2021. Compensation of Rs. 39.817 Cr. against 59.845 Ha land (Part of 321.13 Ha) has been sanctioned on 30/06/2022. Out of 321.13 Ha, till date, Possession of 244.06 Ha. Tenancy land & 35.87 Ha. Govt. land obtained by disbursing Rs. 48.624 Cr. and Rs. 12.74 Cr. respectively. Compensation against remaining 101.05 Ha tenancy land amounting to Rs. 20, 58, 49,126/- has been sanction on 07/06/2023.(Total Possession 497.78 Ha)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks