Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : AMALGAMATED INDER-KAMPTEE DEEP OC (3.20 MTY).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   32.83

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
235.90313.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
116.4600116.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20243/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
12.550

Ministry Review Date

LatestLastPhysical Progress (%)Status
87Ongoing

Monthly Status

Background Information

MoEF&CC issued amendment vis-a-viz amalgamation of EC for a production capacity of 3.20 MTY on 08.06.2020. Out of 857.60 Ha of PR provision, 775.61 Ha (90 %) land is in physical possession.Notification u/s 11(1) issued on 14/06/2022, Gazette Publication issued on 18/06/2022.Land compensation of Rs. 10,38,95,666/- against 58.84 Ha tenancy land has been sanctioned on 06/02/2023. Against this acquisition, entire land Compensation is disbursed. Proposal for land compensation of Rs. 84,48,720/- against 2.62 Ha Govt land is under approval of competent authority. During 2022-23 production is 2.5055 MT.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone