Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : JAGANNATHPUR OC RCE (3.0 MTY).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
459.490459.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
263.56.07-.12263.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20203/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17.470

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Ongoing

Monthly Status

Background Information

Approval of Completion Report of Project Status-Completion Report is under preparation at Area2.831 MT coal production achieved up to Mar’24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone