Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : KOTRE BASANTPUR PACHMO OCP.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
625.4625.4625.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
441.240441.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20320/03/2032

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
43.180

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2441Ongoing

Monthly Status

Background Information

OBR in June 25 OBR Target:0.32 MCUM, Actual:0.15 MCUM 855.17 Ha FC (for Stage II) : Stage II FC issued on 14.03.2024. Payment against WLMP is under process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks