Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : CHANDRAGUPT OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
973.50973.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
339.3200339.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20320/03/2032

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2412.4Ongoing

Monthly Status

Background Information

Stage –II FC issued on 23.04.2025. Stage –II FC compliance is under consideration with ED Nodal since 16.05.2025. 699.38 Ha FC : Proposal recommended to MoEF&CC on 23.02.2024. FAC awaited for Stage - I Early Authentication of tenancy land of villages Chati Bariyatu, Jordag, Bukru, Pachra, Sijhua, Nawakhapunder leasehold area of Chandragupt Project, is required.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone