Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : EPR PUNDI OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
713.350713.35

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
236.5700236.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.870

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2421Ongoing

Monthly Status

Background Information

GMJJ Land involved – 726 acres Earlier, demand note of INR 688 Crore dated 01.09.2021 was raised against 726 acres of GMJJ land by GoJ INR 550 Crore was deposited Revised demand note of Rs 1963.50 crores has been raised. Issue of revised and enhanced demand note for GMJJ land by state govt. is required to be resolved. However, CCL authorities has expressed concerns that imposing commercial rates on agricultural land will adversely affecting the project viability

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone