Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : EPR ROHINI KARKATA OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1020.4201020.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
83.440083.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2411.7Ongoing

Monthly Status

Background Information

Coal Production and OBR in May 25 Coal Target:0.04 MT, Actual:0.05 MT OBR Target:0.14 MCUM, Actual:0.08 MCUM Issue of revised and enhanced demand note for GMJJ land by state govt. is required to be resolved. However, CCL authorities has expressed concerns that imposing commercial rates on agricultural land will adversely affect the project viability.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone