Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : EXPANSION OF ASHOK OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2898.2802898.28

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
175.11.40176.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11.910

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2420Ongoing

Monthly Status

Background Information

Coal Production and OBR in May 25 Coal Target:0.39 MT, Actual:0.45 MT OBR Target:0.51 MCUM, Actual:0.72 MCUM Coal Production and OBR in Mar 24 Coal Target:0.98 MT, Actual:1.02 MT OBR Target:1.01 MCUM, Actual:0.87 MCUM

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone