Project Summary
Project Summary
Sector Name : COAL.
Agency Name : MAHANADI COAL FIELDS LIMITED.
Project Name : SUBHADRA OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1693.8101693.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1179.6.751.621181.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20293/20293/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
37.560

Ministry Review Date

LatestLastPhysical Progress (%)Status
02-MAY-2539.3Ongoing