Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 3.23
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
5
/
5
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| PR approved in 339th meeting held on 28.12.2021 for capital investment of Rs. 324.253 Cr. ( including WDV of Rs. 10.158 Cr.) in partial hiring with 2 CM package. FC proposals for diversion of 101.60 Ha. & 25.866 Ha. have been submitted online. Stage-I FC issued by MoEF&CC for 101.60 Ha. on 26/12/2019. Stage-II FC issued on 27/10/2021. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |