Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : TAWA III UG MINE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   3.23

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
314.090324.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.5600.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.170

Ministry Review Date

LatestLastPhysical Progress (%)Status
9Ongoing

Monthly Status

Background Information

PR approved in 339th meeting held on 28.12.2021 for capital investment of Rs. 324.253 Cr. ( including WDV of Rs. 10.158 Cr.) in partial hiring with 2 CM package. FC proposals for diversion of 101.60 Ha. & 25.866 Ha. have been submitted online. Stage-I FC issued by MoEF&CC for 101.60 Ha. on 26/12/2019. Stage-II FC issued on 27/10/2021.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone