Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : SINGHORI DEEP OC.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   25.64

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
335.750421.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
22.010022.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/03/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
23.110

Ministry Review Date

LatestLastPhysical Progress (%)Status
16Ongoing

Monthly Status

Background Information

The tentative total area involved in the PR is about 740.00 Ha. In addition to this, about 15 Ha land has been proposed for acquisition outside the mine boundary for Saholi village rehabilitation. Thus total land requirement of the project is 755.00 Ha. Out of which 315.13 Ha additional land is proposed to be acquired in the PR. Rest of the land 424.87 Ha is already in possession in the old PR of Singhori OC Mine.In third phase, Notification u/s 7(1) in respect of 315.15 Ha land has been issued on 14/11/2023 and Gazette publication issued on 16/11/2023. Proposal for sec9(1) is under preparation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone