Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 37.36
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
6
/
5
/
1
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| This PR with a capacity of 4.90 MTY was approved in June’ 2022 with a capital outlay of Rs 497.055 Cr with total hiring option including WDV. Notification u/s 7(1) for 37.11 Ha land issued on 19/07/2022.(Old PR). For Makardhokra-I Expansion OC Mine, proposal for notification u/s 4(1) in respect of 161.74 Ha land has been submitted to MoC on 17/07/2023. Notification for section 4(1) issued on 19.09.2023.Proposal of Sec 7(1) for 161.74 Ha sent to MOC on 29.12.2023. Prod. during 22-23 is 4.20 MT. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |