Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 25.71
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
5
/
4
/
1
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Proposal for notification of 510.68 Ha land ( T-479.91+ G-30.77) u/s 4(1) of CBA (A&D) Act, 1957 submitted to MoC on 28/06/2022.Gazette publication issued on 13.08.2022. Notification u/s 7(1) for 510.68 Ha land submitted on 04.11.2022. Notification u/s 7(1) issued on 02.12.2022.Notification for 510.68 Ha land u/s 9(1) of CBA (A&D) Act, 1957, Gazette Publication issued on 17/03/2023. Proposal for notification u/s 11(1) of CBA Act for 510.68 Ha land submitted to MoC on 12/04/2023.Notification u/s 11(1) of CBA Act for 510.68 Ha issued on 19/05/2023, Gazette publication issued on 19/05/2023. Compensation roll under prepration.
RPR for Bhatadi Expansion OC (2.0 MTY) was approved subject to enter in to Coal Supply Agreement on Cost Plus basis with prospective consumers. Cost plus agreement with MAHAGENNCO executed on 19.05.2022 for total quantity. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |