Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : BHATADI EXPANSION OC.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   25.71

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 4 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
580.60729.86

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
61.330061.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
43.160

Ministry Review Date

LatestLastPhysical Progress (%)Status
17Ongoing

Monthly Status

Background Information

Proposal for notification of 510.68 Ha land ( T-479.91+ G-30.77) u/s 4(1) of CBA (A&D) Act, 1957 submitted to MoC on 28/06/2022.Gazette publication issued on 13.08.2022. Notification u/s 7(1) for 510.68 Ha land submitted on 04.11.2022. Notification u/s 7(1) issued on 02.12.2022.Notification for 510.68 Ha land u/s 9(1) of CBA (A&D) Act, 1957, Gazette Publication issued on 17/03/2023. Proposal for notification u/s 11(1) of CBA Act for 510.68 Ha land submitted to MoC on 12/04/2023.Notification u/s 11(1) of CBA Act for 510.68 Ha issued on 19/05/2023, Gazette publication issued on 19/05/2023. Compensation roll under prepration. RPR for Bhatadi Expansion OC (2.0 MTY) was approved subject to enter in to Coal Supply Agreement on Cost Plus basis with prospective consumers. Cost plus agreement with MAHAGENNCO executed on 19.05.2022 for total quantity.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone