Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : NEW MAJARI UG TO OC (3.0 MTY).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   23.39

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 2 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
402.270496.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
47.990047.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
27Ongoing

Monthly Status

Background Information

Notification of 227.23 Ha land u/s 4(1) of CBA (A&D) Act, 1957 in respect of Expansion of NM UG to OC Mine as per PR approved in May 2019 has been issued by Ministry of Coal on 15/01/2020. Gazette Publication issued on 18/01/2020. Notification u/s 7(1) of CBA Act for 224.24 Ha land has been issued on 03/09/2020 and Gazette Publication issued on 05/09/2020. Notification for 224.24 Ha land u/s 9(1) of CBA (A&D), Act, 1957 has been issued on 15/11/2022.Notification u/s 11(1) issued on 27/12/2022 Gazette publication issued on 31/12/2022. Out of 224.24 Ha land Compensation bill against 114.56 Ha tenancy land amounting ot Rs. 22,60,56,964has been sanctioned by FDs on 23/06/2023.Land compensation of Rs 5,07,74,108/-against 25.09 Ha land (part of 224.24 Ha) has been sanctioned by FDs in its 1037th meeting held on 20/09/2023. Land compensation of Rs 15,82,92,260/-against 77.11 Ha land (part of 224.24 Ha) has been sanctioned by FDs in its 1059th meeting held on 27/12/2023. Till date, physical possession obtained is 224.11 Ha, land compensation amount of Rs. 34.884Crore.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone