Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 22.06
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
6
/
4
/
2
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Mine is under operation. EC exists for 1.15 MTY. Out of 650.12 Ha land, 347.460 Ha is in physical possession. In 3rd phase 255.33 Ha Land notified u/s. 7(1) of CBA (A&D) Act, 1957 issued on 21/05/2021. Gazette publication issued on 22.05.2021. Proposal for notification of 252.90 Ha land u/s 9(1) is submitted to MoC on 12/12/2022.Notification u/s 9(1) for 252.97 Ha land issued on 01/02/2023, Gazette Publication issued on 02/02/2023. Notification u/s 11(1) for 252.97 Ha issued on 12/04/2023, Gazette publication issued on 12/04/2023. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |