Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : BHANEGAON OC (1.15MTY).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   22.06

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 6 / 4 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
405.20494.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4.335.88010.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
23.760

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

Mine is under operation. EC exists for 1.15 MTY. Out of 650.12 Ha land, 347.460 Ha is in physical possession. In 3rd phase 255.33 Ha Land notified u/s. 7(1) of CBA (A&D) Act, 1957 issued on 21/05/2021. Gazette publication issued on 22.05.2021. Proposal for notification of 252.90 Ha land u/s 9(1) is submitted to MoC on 12/12/2022.Notification u/s 9(1) for 252.97 Ha land issued on 01/02/2023, Gazette Publication issued on 02/02/2023. Notification u/s 11(1) for 252.97 Ha issued on 12/04/2023, Gazette publication issued on 12/04/2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone