Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : AMALGAMATED DHANKASA JAMUNIA UG (1.84 MTY).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   24.5

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
399.20497.01

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
64.130064.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
22.150

Ministry Review Date

LatestLastPhysical Progress (%)Status
42Ongoing

Monthly Status

Background Information

PR of Amalgamated Dhankasa Jamunia (1.84 MTY) was approved on 19/9/2022 in 345th WCL Board for capital investment of Rs. 497.0062 Crores (including WDV of Rs. 97.8030 Crores ) with targeted capacity of 1.84 MTY at notified price for power sector yielding 18.03% IRR at 85% capacity. Notification U/s. 9(i) for 549.131 Ha (294.293 AR+254.838 MR) notified on 28th February 2013 (includes 85.90 Ha tenancy land in All Rights). Till date, possession of 328.383 (Dhankasa- 70.228 + Jamunia- 258.156) Ha land obtained.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone