Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : GOLETI OPENCAST MINE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 4 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
345.60345.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
67.071.4068.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
125.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
20Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone