Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : GOKUL EXPANSION OC.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 5 / 4 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
309.580456.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3.65003.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.750

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

Project Report of Gokul Extension OC was approved in 331st meeting of WCL Board held on 23.04.2021 with capital investment of Rs. 456.95 Cr. including WDV. Notification u/s 4(1) for 232.36 Ha land issued on 14/06/2022, Gazette Publication issued on 18/06/2022. Proposal for notification of 232.36 Ha land u/s 7(1) of CBA Act has been submitted to MoC on 06.05.2023. Notification u/s 7(1) for 228.12 Ha land issued on 12/07/2023, Gazette Publication issued on 13/07/2023.Proposal of Sec 9(1) for 228.12 Ha sent to MOC on 06.12.2023. Notification u/s 9(1) issued on 23.01.2024 and Gazette Publication issued on 23/01/2024. Proposal for notification u/s 11(1) submitted to MoC on 14/02/2024.. Gazette Publication issued on 01/03/2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks