Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : URDHAN OC.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   10.41

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
206.880228.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
22.120022.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20310/03/2031

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.210

Ministry Review Date

LatestLastPhysical Progress (%)Status
9Ongoing

Monthly Status

Background Information

Project Report for Urdhan Expansion OC Mine (1.00 MTY) was approved by WCL Board in its 344th meeting held on 29.07.2022 for capital investment of Rs. 228.416 Crore (including WDV) on total hiring option with desired selling price to yield IRR of 12% at 85% capacity subject to Cost Plus agreement with prospective consumers. Accordingly, coal supply agreement with MPPGCL was executed on 09.01.2023 for 0.425 MT on cost plus basis.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone