Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : SHARDA UG.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   20.4

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 3 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
166.250200.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.69001.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7.150

Ministry Review Date

LatestLastPhysical Progress (%)Status
11Ongoing

Monthly Status

Background Information

Project Report for Sharda UG (0.51 MTY) was approved by WCL Board in its 344th meeting held on 29.07.2022 for capital investment of Rs. 200.160 Crore (including WDV) on equipment hiring option with desired selling price to yield 12% IRR at 85% capacity subject to cost plus agreement with prospective consumers. Accordingly cost plus agreement was executed on 05.09.2023 with MPPGCL for 0.4335 MTY.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone