Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : KOLGAON EXPANSION (DEEP) OC.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   3.76

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.710206.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.5500.55

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.650

Ministry Review Date

LatestLastPhysical Progress (%)Status
5Ongoing

Monthly Status

Background Information

Project Report for Kolgaon Expansion (Deep) OC (0.80 MTY) was approved by WCL Board in its 348th meeting held on 28.01.2023 for capital investment of Rs. 206.194 Crore (including WDV) on total hiring option with desired selling price to yield IRR of 12% at 85% capacity subject to Cost Plus agreement with prospective consumers. Accordingly, coal supply agreement with MAHAGENCO was executed on 23.09.2023 for 0.68 MTY on cost plus basis.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone