Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : NLCIL 300 MW SOLAR POWER PROJECT (PART OF 510 MW CPSU SCHEME).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 6 / 4 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
181301813

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
579.82075.12654.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20240/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
07-MAY-2566Ongoing

Monthly Status

Background Information

*Switchyard, MCR & ICR civil finishing works completed and testing at switchyard is under progress. *BOS material supply completed for 99% & PV Module supply inspection is under progress. MDCC issued for 53 MW and 42.16 MW received at site. 2.5 MW Module is installed and work under progress. *Bay Extension at BTPS Substation: Foundation for equipments and transmission lines towers completed. Erection works under progress (5 Nos of tower erected out of 5nos of Transmission line towers). Equipment supply completed for 90%. Equipment erection is under progress. Boundary Fencing, Drainage, Peripheral Road works is under progress *On 23.05.2025, IREDA issued EOT upto 31.12.2025 to NLCIL. 1) Power Usage Agreement (PUA) signed with RUVNL at a tariff of Rs. 2.52/Unit. 2) LOA issued to M/s Tata power solar systems (TPSSL) on 27.03.2023. Contract signed on 07.06.2023. 3)Geo Technical & Topological survey completed. Site boundary fencing works started. 4)MMS Material supply started and is in progress. Application for 1st Tranche of VGF for 310 MW was submitted on 06.09.2023. 5)220KV Switchyard, MCR (Main Control Room) roof slabs casted ICR (Inverter control room) under progress. 5 nos. IDT placed on foundation. 6)Switchyard- 2 Nos Power Transformer is placed on the foundation other Civil works of equipment foundation are under progress. 7)Construction Power and water supply provided to M/s TPSSL. 8)Casting & erection of fencing posts are under progress. 9)Inspection of Plant and Equipment’s are underway, Inverters supply completed. (108 Nos out of 108 Nos received at Stores). 3 Nos Power Transformers and 8 Nos IDTs arrived at site

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone