Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : NLC TALABIRA THERMAL POWER PROJECT (PHASE-1: 3 X 800 MW).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    10

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
27213027213

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1556.04.42326.931883.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20293/20303/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
25-MAY-251.55Ongoing

Monthly Status

Background Information

*280 Nos. PDFs of Hirma &Kumbhari village have been allotted houses in R&R Colony. 223 PDFs have been shifted to R&R Colony. 66 PDFs have opted for self-relocation. For Tareikela village, 110 Acre of land payment has been completed and further 102 Acre of land payment is under progress. *R&R Colony (In Jharsuguda District- 104 Ac.):As per SIA study, there are 762 PDFs in Project area. Construction of 322 houses is under progress in 63.74 Ac out of 104 Ac, as the balance 40.47 Ac. land is not suitable for taking up construction work for remaining houses to accommodate the PDFs’ of Tareikela village. Work is under progress on 13.53 Ac. land. NLCIL has applied for 50 Ac. of land to Dist Admin. for construction of balance houses for R&R colony. IPICOL has accorded approval for 50 Ac. Land. Topo survey completed. Demarcation done on 29.04.2025. Soil investigation work is under progress in 50 Acre of land. NLCIL requested MD/IDCO for exchange of the 50 Ac. land with other suitable land. a) Main Plant area (In Jharsuguda District- 880 Ac.) 48 nos. PDFs have been Shifted to R&R Colony. 12 nos. original PDFs houses demolition of shifted PDFs in the Hirma village completed. House allotment of balance 49 PDFs of Hirma village completed. Top soil removal of agricultural land is under progress. b) b) R&R Colony (In Jharsuguda District- 104 Ac.): Tree enumeration works are under progress. Dist. Admin is processing the lease proposal. R&DM has sanctioned lease order for 20.95 Ac. Govt. land (C Block) sanction to NLCIL. The R&R colony construction work is under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone