Project Summary
Project Summary
Sector Name : COAL.
Agency Name : EASTERN COAL FIELDS LIMITED.
Project Name : HURA C OC.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
859.410859.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
440.28.4.12448.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/03/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
57.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
11-JUN-2562Ongoing

Monthly Status

Background Information

Total Coal Production for the month of June 2025:0.224 MT

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks