Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : 50 MW SOLAR POWER PROJECT -NEYVELI MINED OUT AREA.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 5 / 3 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
218.030218.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
137.84010.15147.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
07-MAY-2538Ongoing

Monthly Status

Background Information

*Boundary fencing works started on 29.07.2024 and under progress and 2.2 km/6.5 km completed. *Piling works in progress in all four sites. (14,719/27,495 Nos completed).IDT foundation works under progress (4/6 Nos completed up to NGL level). *MMS structure material supplying is under progress. *DC Cable laying, SCMB, table to table earthing strips laying is under progress. *BoS Material supply under progress. Erection of PV module tables is under progress. Module erection in tables started from 28.04.2025 and 431 modules erected.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone