Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : 50 MW SOLAR POWER PROJECT -NEYVELI MINED OUT AREA.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
218.030218.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.09297.24-159.49137.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0120

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-MAR-2537Ongoing

Monthly Status

Background Information

*Piling works in progress in all four sites. (8593/27495 Nos completed). IDT foundation works under progress. *MMS structure material 1000 MT received out of 1762 MT, 6 sq.mm DC cable - 292 KM DC (1c x 6sqmm) received and 100% Inverter supply to the site is completed (4.4MVA- 10 N’s and 3.3 MVA- 4 No’s).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone