Project Summary
Project Summary
Sector Name : COAL.
Agency Name : MAHANADI COAL FIELDS LIMITED.
Project Name : RPR OF HINGULA EXPANSION OCP.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1561.8501561.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
43.334.161.6149.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/03/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
116.680

Ministry Review Date

LatestLastPhysical Progress (%)Status
02-MAY-253.57Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone