Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1. As suggested by DGMS for amalgamation of mines of Block-E OCP, Technical Audit for Block-E OCP is being done by IIT(ISM), Dhanbad. Draft Technical Audit report has been submitted on 30.05.2025 and is under scrutiny.
2. Work Order has been issued to IIT(ISM), Dhanbad on 27.03.2025 for conducting Scientific Study for Jore Diversion in order to obtain NOC from Water Resource Department. IIT(ISM) Team hosted a meeting with Block-E Team on 15.04.2025 to commence the study. The team visited mines of Block-E OCP on 03.05.2025 to see the topography and feasibility of Jore Diversion.
3. Land schedule for land requirement during first five years of project life has been prepared as per available CS Record and is under vetting process. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |