Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : 50 MW WIND POWER PROJECT PART OF 150 MW SECI HYBRID.

Reported Date : 16-MAY-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
383.840383.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
272.07031.43303.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20251/20261/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
07-MAY-2541Ongoing

Monthly Status

Background Information

*Sublease agreement for land (19 plots) was signed. 2 Nos of plot details submitted which is cleared by NLCIL legal team and requested Contractor to submit the ROW for signing the lease agreement. Balance 4 Nos of plot yet to be identified. * Wind mills blade 25 sets, Tower sets 25 sets& Hub and Nacelle 23Nos have received at site. *Foundation works completed for 8Nos. & 2Nos work under progress. Erection of 6 WTG Completed. *Work Order issued to Ms Tectra Engineering build Pvt.Ltd as Owners Engineer Consultant. *Connectivity application accepted by M/s CTUIL in the consultative committee meeting held on 02.07.2024. Inprinciple Grant received from M/s CTUIL on 09.08.2024. *On 31.05.2025, CMD/NLCIL sent a request letter to SECI Extension of Time up to 31.07.2026.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone