Reported Date :
16-MAY-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
7
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
*Sublease agreement for land (19 plots) was signed. 2 Nos of plot details submitted which is cleared by NLCIL legal team and requested Contractor to submit the ROW for signing the lease agreement. Balance 4 Nos of plot yet to be identified.
* Wind mills blade 25 sets, Tower sets 25 sets& Hub and Nacelle 23Nos have received at site.
*Foundation works completed for 8Nos. & 2Nos work under progress. Erection of 6 WTG Completed.
*Work Order issued to Ms Tectra Engineering build Pvt.Ltd as Owners Engineer Consultant.
*Connectivity application accepted by M/s CTUIL in the consultative committee meeting held on 02.07.2024. Inprinciple Grant received from M/s CTUIL on 09.08.2024.
*On 31.05.2025, CMD/NLCIL sent a request letter to SECI Extension of Time up to 31.07.2026. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |