Project Summary
Project Summary
Sector Name : FERTILISERS.
Agency Name : RASHTRIYA CHEMICAL & FERTILISER LIMITED.
Project Name : THAL AMMONIA REVAMP PROJECT.

Reported Date : 16-JUL-12

Monthly Report : 5 / 2012

  

   

Total/Pending/Completed Milestone - 22 / 0 / 22

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
488.750488.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
305.36.941.59307.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20124/20124/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
145.70

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

1. Schedule Monthly Physical Progress - 0.10% 2. Acutal Monthly Physical Progress -0.10% 3. Schedule Cumulative Physical Progress - 100% 4. Acutal Cumulative Physical Progress - 100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks