Project Summary
Project Summary
Sector Name : FERTILISERS.
Agency Name : NATIONAL FERTILISER LIMITED.
Project Name : PANIPAT - AMMONIA PLANT FEEDSTOCK CHANGEOVER PROJECT.

Reported Date : 19-MAR-13

Monthly Report : 1 / 2013

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1292.8401292.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
530.91415.0941.72987.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20130/01/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5600

Ministry Review Date

LatestLastPhysical Progress (%)Status
19-NOV-12100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks