Project Summary
Project Summary
Sector Name : FERTILISERS.
Agency Name : NATIONAL FERTILISER LIMITED.
Project Name : CAPACITY ENHANCEMENT OF VIJAIPUR-I PLANTS.

Reported Date : 04-FEB-13

Monthly Report : 12 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3250325

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
48.19136.910185.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20110/012/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
07-FEB-12100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks