Note: i) The increase in the Project Capital Cost is mainly due to non-issuance of Project Import Status and payment of advance rentals to Govt. Bodies like PWD, Railways etc. This is an estimated value. Actual project capital cost can be known only after the project is completed. As on 31.01.2020, the project capital expenditure since inception is Rs.188.89 Crore. Hence, as on date there is no cost overrun.
ii) Actual Completion dates : Commissioning – new STP : 10.09.2019, Performance Tests – new STP : 27.12.2019, Commissioning – new SPS : 10.01.2020, Performance Tests – new SPS : 22.01.2020.
iii) Milestone/s achieved during the month : SPS – 45.5 MLD SPS at Ghatkopar – Commissioning and SPS – 45.5 MLD SPS at Ghatkopar – Performance Guarantee Test Runs (GTR).
iv) Status of Critical milestones due up to month but delayed: Nil
v) Employment Manpower : Average 10 contract labour per day during the month of Dec. 2019.
Project is complete. | |