Project Summary
Project Summary
Sector Name : FERTILISERS.
Agency Name : RASHTRIYA CHEMICAL & FERTILISER LIMITED.
Project Name : GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT RCF THAL..

Reported Date : 15-MAY-19

Monthly Report : 3 / 2019

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
482.850433

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
41317.862.14433

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20170/03/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

PRELIMINARY ACCEPTANCE CERTIFICATE - Issued w.e.f 07-March-19. Project Completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks