Project Summary
Project Summary
Sector Name : FERTILISERS.
Agency Name : NATIONAL FERTILISER LIMITED.
Project Name : GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT NFL BATHINDA.

Reported Date : 07-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 2 / 1 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
218.830218.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
187.5212.970200.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks