Reported Date :
10-AUG-22
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
7
/
2022
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
27
|
Total/Pending/Completed Milestone -
14
/
0
/
14
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
I. Milestones achieved since Project started (i.e. 18th April 2018) up to month (Jul’22):
81. Mechanical Completion – 20-Mar-21
82. HRSG#2 – Full Load Operation – 25-Mar-21
83. GTG#2 – Commissioning – 22-Sept-21
84. GTG#1 – Commissioning – 25-Sept-21
85. Train 2 – RRT & PG Test – 09-Oct-21
86. Instrumentation System – DCS Commissioning – 19-Oct-21
87. Train 1 – RRT & PG Test – 19-Oct-21
88. Issuance of Preliminary Acceptance Certificate (PAC) – 22-Jul-22
GTG-HRSG Project at Trombay, Mumbai is 100% completed. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | &nb |