Project Summary
Project Summary
Sector Name : MINES.
Agency Name : NATIONAL ALUMINUM COMPANY LIMITED (NALCO).
Project Name : Implementation of 50.4 MW Wind Power Project at Jath, Sangli, Maharashtra.

Reported Date : 10-JAN-18

Monthly Report : 11 / 2017

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
355.13355.13355.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
355.1300355.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/201612/201611/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project completed in all respect.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks