Project Summary
Project Summary
Sector Name : MINES.
Agency Name : NATIONAL ALUMINUM COMPANY LIMITED (NALCO).
Project Name : IMPLEMENTATION OF 50 MW WIND POWER PROJECT AT RAJASTHAN.

Reported Date : 10-JAN-18

Monthly Report : 11 / 2017

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
344.5344.5344.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
344.500344.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/201611/201611/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks