1. Acquisition of Pvt. land of OLCC: Field work for SIA study started by NCDS on 20.06.2025.
2. Alternate Road to Pottangi Mines: DFO, Koraput sought some additional documents w.r.t. Forest Diversion Proposal of Alternate Road to Pottangi Mines on 25.06.2025. Compliance submitted on 01.07.2025. Proposal forwarded to PCCF (Nodal) on 02.07.2025.
3. Tender floated in CPP Portal for Selection & Engagement of MDO for Pottangi Bauxite Mines on 20.06.2025.
| 1) Dept of Steel & Mines, GoO on 06.03.2024 has issued the extension order for execution of Mining Lease upto 21.08.2024.
2) The revised demand of Stamp duty and Registration charge of Rs. 18,59,86,096.00 and Rs.7,43,94,439.00 respectively was received from O/o Sub Registrar Pottangi on 19.03.2024 and the same was paid on 22.03.2024.
3) The draft Lease Deed along with a duplicate copy for mining lease execution submitted to DDM Koraput on 27.03.2024.
4) Stage -I compliance for FC of OLCC submitted to DFO Koraput on 28.03.2024 for obtaining Stage – II FC.
5) Stage – I Compliance for FC of Water intake facility submitted on 01.03.2024 for obtaining Stage – II FC.
|