Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REBUILIDING OF COKE OVEN BATTERY-10.

Reported Date : 25-NOV-10

MOU Status :

Monthly Report : 9 / 2010

Cost Overrun (%)-   4.81

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
416.5436.54436.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
250.5651.173.41305.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20090/08/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1200

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone