Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : SIMULTANEOUS BLOWING OF BOF CONVERTER OF SMS-II.

Reported Date : 28-MAR-11

MOU Status :

Monthly Report : 1 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
197.660197.66

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
107.6422.680130.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20090/010/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2540

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed