Reported Date :
04-FEB-15
|
MOU Status :
Project Under MOU for 2014-2015
|
Monthly Report :
12
/
2014
|
Cost Overrun (%)- 13.61
|
Time Overrun (Months)-
36
|
Total/Pending/Completed Milestone -
29
/
0
/
29
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
15787.87 | 754.02 | 98.99 | 16640.88 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Facilities under the integrated process route are in operation and are under stabilisation . | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |