Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : EXPANSION OF IISCO STEEL PLANT.

Reported Date : 04-FEB-15

MOU Status : Project Under MOU for 2014-2015

Monthly Report : 12 / 2014

Cost Overrun (%)-   13.61

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 29 / 0 / 29

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
14443016408

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
15787.87754.0298.9916640.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20110/012/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Facilities under the integrated process route are in operation and are under stabilisation .

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone